Frequently Asked Questions
Q: What is building air leakage?
A: Air leakage is the uncontrolled flow of
air through gaps and crack in the fabric of
the building, not to be confused with ventilation,
which is the controlled flow of air into and
out of the building through purpose built ventilators.
Q: What is the detail behind the new
regulations relating to Air Tightness Testing
for domestic properties?
A: Gaps and cracks in the building fabric
are often difficult to detect simply by visual
inspections. Air leakage paths through the building
fabric can be torturous; internal building finishes
or external cladding often obscure gaps. The
Approved Document L1 A 2006 requires that all
new dwellings have an acceptable CO² emissions
rate referred to as the Dwelling Emission Rate
or DER. Part of the calculation procedure required
to determine the DER refers to the actual leakage
of air from the building. The lowest acceptable
standard under building regulations is 10m³/(h.m²)@
50 Pascals. Building control bodies only accept
certificates from BINDT registered airtightness
testers as evidence that the procedure has been
followed.
Q: Why do we have test for airtightness
in domestic properties?
A: Because proving the airtightness of a building
is now part of the building regulation process.
Domestic energy accounts for more than 25% of
the U.K’s CO² emissions and Government
currently aims to reduce CO² emissions
by 20%-28% by 2010.
Q: I have a small development of 4
similar properties, how many of these do I need
to have tested?
A: One
The guidelines state the following number of
tests per dwelling type are required:
4 or less of the same style : 1
5 to 40 dwellings : 2
More than 40 dwellings : At least 5% unless
the first five units/dwellings meet the prescribed
standard then the sample size can be reduced
to 2%
Q: Are there any exceptions?
A: Yes, several a single dwelling is exempt
if the same style has been constructed in the
proceeding 12 months by the same builder and
can be shown to have achieved the prescribed
standards of air tightness. Although note, the
building control officer will decide which and
how many units are actually tested. The need
for Air Tightness Testing can also be avoided
(for a development of no more than 2 dwellings)
by using the default value of 15m/³/ (h.m/²)
for the air permeability at 50Pa when calculating
the DER in the SAP calculations. This will necessitate
the use of improved standards of insulation
or higher efficiency equipment with associate
additional costs.
Q: Do extensions need to be tested?
A: Where an extension is proposed to an existing
building with a total useful floor area over
1000 sq.m. the building is to be upgraded, insofar
as it is technically, functionally and economically
feasible to meet the requirements of Part L.
(This is to meet the requirements of Article
6 of the Energy Performance of Buildings Directive).
For average dwellings, therefore, pressure testing
of extensions is unlikely to be required. BUT
watch this space, as it could be a key area
for the Government to use in reducing CO²
emissions.
Q: When should Air Tightness Test take
place?
A: Air tightness testing should be conducted
during the latter stages of construction of
the first 25% of each new dwelling type. There
are clear benefits to the principle contractor
that the airtightness of a development is assessed
at the earliest opportunity to ensure there
is compliance with best practice.
Q How much does Air Tightness Test cost?
A: It depends on the size and complexity of
the property, the location and the level of
preparedness of the building. The cheapest quote
is not always the best as re-tests can be expensive.
It’s useful to consider several U.K studies
have shown that improved and demonstrable property
airtightness can yield energy savings of 15%
to 30%. This should result in a higher sale
price for the property because of on going reduced
energy costs.
Q: How long does typical domestic Air
Tightness Test take?
A: It depends on the size of the property,
how many apertures need to be taped over and
if you are able to provided a full set of plans
(preferably in an electronic format) But the
duration of the actual test should take no longer
than two hours. If the property passed the Airtightness
test a certificate will normally be available
within 7 days of the test being completed.
Q: What happens if an Air Tightness
Test fails?
A: Should a dwelling fail to meet the required
standards of air permeability, then the weakness
should be identified (there are a number of
particularly common areas) Remedial work should
be carried out. The regulations state that for
each dwelling which fails the air tests on an
accredited build, a re-test of the failed build
plus an additional dwelling of that design should
also be tested. For non-accredited builds, a
re-test of the building plus two additional
dwellings of the same type must also be tested.
(Accredited Construction Details are available
for free download from the Communities and Local
Government website) - www.communities.gov.uk
Q: So how do you actually measure Air
leakage?
The pressure differential is measured across
the envelope of the building by means of a large
fan installed temporally, usually in a doorway.
All relevant openings into the property are
temporally sealed and a range of static pressures
and environmental readings are taken. The fan
is switched on and the air pressure in the property
is gradually increased or decreased and the
differential pressure is recorded at each step.
Employees can continue work within the property
but all windows and doors have to remain closed
for the duration of the test. The total air
flow required to achieve a pressure differential
of 50 Pa is calculated and divided by the total
building envelope area to provide the leakage
rate in m³/h.m²)@50Pa.
For further information or a free quote,
please call 08456 43-97-32 / 07946 315 721 or
email info@ryedale-att.co.uk
|